Monday, October 16, 2006

Helpers, Helpers

Things are moving along now, thanks to help from a lot of people. This weekend, Kenny's Dad, brother, and friend Brian pitched in - working on the ductwork. Below, Kaden measures and marks for Mommy!

Above and below - progress on the ductwork.

Above - Brian and Kenny working on the ductwork. Below - the new garage doors were installed on Saturday. We haven't taken the protective plastic off yet, but you get the idea.

Wednesday, October 11, 2006

Tanks and Trim

Here's Kenny still working on the roof trim - getting the most out of our nice, but shorter fall days
Below is the underground propane tank.
Just before sunset: a view of the south side with the covered underground cistern on the left. Today a water truck came and put some water in to keep it from floating until we attach all of the fittings and backfill it.

Wednesday, October 4, 2006

More mud and Roofing

The new driveway base is down!

Above: the electric line and trench just before inspection.
Below: Kenny and I finished most of hte garage roofing. There's three pieces that we're waiting for and then a few trim pieces. .


Above: The electric trench where it meets the house. This is where the electric meter and panel will be.

Below: A view of the current state of our front yard.

Monday, October 2, 2006

Weekend Work Update

Above: A nice morning view of our east side shade trees. These trees on the south-east side help to keep the house cool in the summer. The kids are having fun playing in the mud.
Below: Kenny and his Dad begin working on the garage roofing.


Above: The rainwater catchment tank (cistern) was delivered on Friday morning. It's a 1700 gallon tank and will be installed undergrond to hold water for our toilet flushing, washing machine, and outdoor hose spigots.

Below: A quick sneak onto the neighbor's property gives us this peek at the new house roof. There's only one piece left to finish, but it's a cut piece so we need to get some electric shears to cut it. This is basically the view of the house from the road too, but eventually we'll fill in the lower part with some nice landscaping.

Friday, September 29, 2006

Sewer Line Passes Inspection

Here are a few more pics of the sewer line going in. The tap in went well and we passed the before and after inspection. The inspector asked if he could be included on our first tour. Anyway, then the sewer/water contractor spent the rest of the day filling the trench back in. He finished up about 6:30 pm - just before Kenny and crew finished the roof. Then of course it started raining, so he probably won't start digging for the water line or electric until next week or later, since it calls for rain all next week too. Augh!
Now don't try this at home folks . . .
This weekend we hope to finish up the house roof and continue with HVAC inside. If we're really lucky, we might get to the garage roof or the rest of the house roof trim????

Thursday, September 28, 2006

A Day Made for Roofing

Today was a beautiful early fall day. It was just one of those perfect days - not too hot, not too windy, but a nice breeze, and a nice blue sky with a few white clouds. Kenny, his brother, and his Dad literally spent from sun up to sun down putting roofing on today. Rain is expected tonight and tomorrow (actually there's a thunderstorm going through right now), so they tried to get as much finished as possible. There's about 10 pieces left that need to be finished - hopefully if the rain clears out, we can get those down in the next few days. We still have the garage roof and some trim pieces to do, but you can see from the picture above that the standing seam metal roof really has a nice clean look to it.
I spent the day taking pictures and "getting stuff." Above you can see what was my view from the highest point on the house roof looking north to the Tealtown Baseball Fields. Our shed is in the lower right. Below is Kenny securing down a piece of roofing. Below you can see the Nutter boys. Kenny is farthest down, his Dad is in the middle, and his brother is closest. They really had a system going!
Below is a view looking up from the ground. Can a sky get any more blue? This is as they were working on the first few pieces on the east end.

All in all it was a very productive, but tiring day. Kenny's Dad loved the fact that he had both of his sons working with him and not once did any of them try to throw another off the roof! I've got some more pictures of the progress on the sewer line and excavation that I'll post tomorrow. It's almost 10pm so we're heading to bed for some well-deserved rest. Kenny's Dad and brother probably still have another hour before they get home, so if you know them, make sure you tell them they did a good job today!

Tuesday, September 26, 2006

Progress Pictures

Above: The north side of the house. Notice the roofing stacked on the garage roof. Below: The shed is almost finished! We just have a few trim pieces, cleaning some dust off, and some touch up paint.

Trenching for sewer line.