Below is the garage footing and stem wall before the pour and above is after the concrete pour and sealer
 And now FINALLY some actual walls!  Above is a view from the great room back to the kitchen.  Below is a view from the corner of the great room back toward the dining room.
 In the pic above, the south wall goes up.  Below . . . You remember when I mentioned the pool, right?  (We'll be pumping that out as soon as we get dried in). 
 We're supposed to have all of the first floor framed (except for the two-story great room) tomorrow.  The open-web floor trusses arrive for installation tomorrow - weather permitting.  Then, they'll be able to move on up to the second floor, the geat room, and finally the roof.  We'll keep you posted.  Thanks for reading!